Francis Scott Key Bridge Now Set to Reopen Late 2030
MDTA says the Francis Scott Key Bridge rebuild estimate is now up to $5.2B with a projected opening late 2030, reflecting new safety standards & rising costs.
Maryland Updates Cost and Timeline for Francis Scott Key Bridge Rebuild
Francis Scott Key Bridge Rebuild Now Up to $5.2 Billion
Maryland officials have released updated information about the plan to rebuild the Francis Scott Key Bridge. The Maryland Transportation Authority (MDTA) now estimates the project will cost between $4.3 and $5.2 billion. The agency also expects the rebuilt bridge to open to traffic in late 2030.
These new estimates were created with support from the Federal Highway Administration. They replace the early estimates that were made less than two weeks after the collapse of the Francis Scott Key Bridge in March 2024.
Acting Transportation Secretary and MDTA Chair Samantha J. Biddle said the increased cost is tied to rising material prices and new safety needs. “The new Francis Scott Key Bridge isn’t just a local infrastructure project – it’s vital to our nation’s economy and will connect the Baltimore region to economies throughout the United States and the world,” she said.
New Safety Standards Shape the Design
The updated plan for the Francis Scott Key Bridge must meet today’s federal safety standards. One major change is the longer main span, which will now measure 1,665 feet. This gives more room for the larger cargo ships that pass through the Port of Baltimore.
The bridge will also include a stronger pier protection system. MDTA said the new protective fenders are larger than a football field. These structures are designed to protect the bridge’s main piers and help prevent another ship strike. The early estimates did not include the full cost of this system.
Taller towers are also part of the updated design. They are needed to support the deck, which will sit about 230 feet above the water. These changes help the project meet the most current guidelines for modern bridges.
Rising Costs Affect the Francis Scott Key Bridge Project
Construction costs continue to climb across the country. The Federal Highway Administration reports that highway construction prices have increased about 72% in the last five years. Inflation, material shortages, and labor challenges all add pressure to large projects.
Contractors often raise their bids to cover sudden changes in material or labor prices. This increases overall project risk and affects long-term cost planning.
MDTA Executive Director Bruce Gartner said the earliest estimates were created quickly so the state could receive emergency funding. “Less than two weeks after the collapse, a preliminary estimate was needed to request federal emergency relief funding for immediate clean up and recovery,” he said.
Gartner also noted the fast progress of the design work. He said the Francis Scott Key Bridge rebuild reached 70% design completion in 14 months, which is much faster than typical projects of this scale.
Federal Aid Will Fully Support for the Rebuild
The Francis Scott Key Bridge project is covered under the federal Emergency Relief Program, part of the American Relief Act. The program provides more than $8 billion for emergency recovery work. It also covers 100% of eligible costs for this rebuild.
Maryland will still advance construction costs and apply insurance funds to the project. The state continues legal action against the Dali’s owner and manager for damages related to the bridge collapse. Any money recovered from the lawsuit will reduce the amount taken from the federal emergency fund.
Officials said they want the responsible parties to cover the damages caused by the incident.
Progress Continues on the Francis Scott Key Bridge Rebuild
Design and early construction work for the bridge continues to move forward. MDTA said its teams are working around the clock. Groundbreaking for the new bridge is expected within the next several months.
The loss of the Francis Scott Key Bridge has caused traffic delays, longer commutes, and challenges for local businesses. MDTA plans to keep providing real-time travel updates and will adjust transportation operations to help reduce impacts as work continues.
Officials said the state will remain focused on supporting the region throughout the rebuild process.